Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 273
Message text: Kostenrechnungskreis &1 weicht von dem des Projekts/Kd.auftrags (&2) ab
You want to explode a material BOM and allocate BOM items to a network
activity in a project (sales order).
The plant for the BOM is assigned to controlling area &v1&, but the
project (sales order) is assigned to controlling area &v2&.
You can only make allocations within the same controlling area.
Select a BOM from a plant in the same controlling area as the activity.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CN273
- Kostenrechnungskreis &1 weicht von dem des Projekts/Kd.auftrags (&2) ab ?Get instant SAP help. Sign up for our Free Essentials Plan.
CN272
Kostenrechnungskreis &1 des Werkes weicht von dem des Netzplans (&2) ab
Was verursacht dieses Problem? You want to explode a material BOM and allocate BOM items to a network activity. The plant for the BOM is assigned t...
CN271
Es bestehen noch Komponentenzuordnungen zum Einzelbestand
Was verursacht dieses Problem? You want to delete the assignment of a network header or an activity to a WBS element or a sales order item. However...
CN274
Positionstyp &1 ist für &2 nicht vorgesehen
Was verursacht dieses Problem? You are using item category &v1& for creating a new component. This category is not intended for &v2&...
CN275
Für Material &1 Werk &2 existieren keine Daten zur Parametergültigkeit
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.