How To Fix CN079 - Profitcenter der PSP-Elemenete müssen übereinstimmen


CN079 - Overview

  • Message type: E = Error

  • Message class: CN - Meldungen für Netzpläne

  • Message number: 079

  • Message text: Profitcenter der PSP-Elemenete müssen übereinstimmen

  • Show details Hide details
  • Was verursacht dieses Problem?

    A. You want to change the WBS element of a component.
    Profit Center Accounting is active within the scheduled network dates
    for the controlling area of the WBS elements. The WBS element you
    entered is assigned to a different profit center than the original WBS
    element.
    B. You want to reallocate a component that is assigned to a WBS element
    to another activity.
    Profit Center Accounting is active within the scheduled network dates
    for the controlling area of the WBS elements. The WBS element of the
    component is assigned to a different profit center than the target
    activity's WBS element.

    Wie behebe ich diesen Fehler?

    A. Choose a WBS element with the same profit center.
    B. Choose an activity with a WBS element from the same profit center.

    Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE


CN079 - Details








Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Zugehörige SAP-Fehlermeldungen

Klicken Sie auf die Links unten, um die folgenden verwandten Nachrichten anzuzeigen:

Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author