Message type: E = Error
Message class:  CN - Meldungen für Netzpläne 
Message number: 054
Message text: Kostenrechnungskreis konnte nicht ermittelt werden
No controlling area could be determined for the activities in the
network.
The system requires a controlling area in order to make it possible to
display the costs for an activity. The controlling area is determined
for activities in the network as follows:
For general costs activities, the controlling area is determined using
the company code to which the general costs activity in the network
profile is assigned.
For internally and externally processed activities, the controlling
area is determined from the plant to which the network is allocated.
Maintain a key for the company code on the cost detail screen for the
general costs activity.
Maintain a key for the plant on the activity detail screen for the
internally and externally processed activities.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
 Get instant SAP help. Sign up for our Free Essentials Plan.
Get instant SAP help. Sign up for our Free Essentials Plan. 
CN053 Netzplan hat keine Vorgangskontierung
Was verursacht dieses Problem?    You cannot write any costs to the activity for this network. You can only write costs to the network header for the ...
CN052 Steuerschlüssel ist nicht vorhanden
Was verursacht dieses Problem?    The control key you entered does not exist.Systemantwort   INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID...
CN055 Netzplan ist nicht vorhanden (Prüfen Sie die Eingabe)
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
CN056 Vorgangskontierung für diesen Netzplan nicht erlaubt
Was verursacht dieses Problem?    You cannot write any costs to the activity for the network whose key you have maintained. The costs for the network ...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.