Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 588
Message text: Endtermin der PSP-Elemente liegt nach dem Endtermin der Projektdefinition
You entered a finish date for the WBS element after the finish date in
the project definition. Since the start and finish dates in the project
definition are not binding, processing has not been stopped.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CJ588
- Endtermin der PSP-Elemente liegt nach dem Endtermin der Projektdefinition ?Get instant SAP help. Start your 7-day free trial now.
CJ587
Starttermin der PSP-Elemente liegt vor dem der Projektdefinition
Was verursacht dieses Problem? You entered a start date for the WBS element that is before the start date in the project definition. Since the star...
CJ586
Zeitprofil & nicht vorhanden
Was verursacht dieses Problem? In a Gantt chart, you can only delete WBS elements.Systemantwort INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT...
CJ589
Keine Termine zum PSP oder zur Projektdefinition vorhanden
Was verursacht dieses Problem? There must be a time frame in order for you to enter activities for a WBS element. It can come from the: WBS element...
CJ590
Maßstab & für Zeitachse ist nicht vorhanden
Was verursacht dieses Problem? There is no scale for the time axis &V1&.Systemantwort INCLUDE 'NA_ALLG_NOVERARBEITUNG OBJECT DOKU ID...