Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 560
Message text: Ende des Vorgangs liegt nach dem Endtermin des PSP-Elements &
The finish date that you entered for the activity is later than the
finish date for the WBS element.
You cannot adjust the dates from top to bottom.
Enter a finish date for the activity that is earlier or the same as the
finish date for the WBS element.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CJ560
- Ende des Vorgangs liegt nach dem Endtermin des PSP-Elements & ?Get instant SAP help. Start your 7-day free trial now.
CJ559
Start des Vorgangs liegt vor dem Starttermin des PSP-Elements &
Was verursacht dieses Problem? The start date that you entered for the activity is earlier than the start date of the WBS element.Systemantwort Y...
CJ558
Feldüberlauf bei der Berechnung der Dauer des Projekts &
Was verursacht dieses Problem? An internal error has occurred while calculating the duration of project definition &V1&.Systemantwort The...
CJ561
PSP-Element & hat Vorgänge. Bitte zuerst Vorgänge löschen
Was verursacht dieses Problem? You can only delete the dates in a WBS element if there aren't any activities assigned to the WBS element anymo...
CJ562
Bitte zuerst alle Vorgänge terminlich abgleichen
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.