Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 541
Message text: PSP-Element & muß Kontierungselement sein
The activity or activities that you want to assign to a WBS element, are
in a network with an account assignment. The WBS element must also be
an account assignment element in order for you to assign it (them),
You cannot make any actual or open item postings to the WBS element &V1&
because it is not defined as an account assignment element.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Enter a WBS element that is defined as an account assignment element.
If you really want to post to WBS element &V1& then you must first have
it changed to an account assignment element by an authorized person
(for example, the system administrator).
Procedure for the system administrator:
Define the WBS element &V1& as an account assignment element.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CJ541
- PSP-Element & muß Kontierungselement sein ?Get instant SAP help. Start your 7-day free trial now.
CJ540
Keine Netzplanzuordnung für PSP-Element & gepflegt
Was verursacht dieses Problem? When you enter dates in time scheduling, the system creates a network with these dates in the background. You must e...
CJ539
Keine Vorgangselemente zu den markierten Vorgängen gefunden
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
CJ542
Neuer Starttermin ist grösser als der alte
Was verursacht dieses Problem? You can only enter an earlier start date.Systemantwort INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID T...
CJ543
Keine Terminänderungen vorhanden
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.