Do you have any question about this error?
CJ
›
CJ527
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 527
Message text: Endtermin liegt nach Endtermin & des übergeordneten PSP-Elements
The finish date that you entered for the WBS element is later than
finish date &V1& of the superior WBS element.
INCLUDE 'NA_ALLG_VERARBEITUNG' OBJECT DOKU ID TX
If you use top-down planning and shift the dates, the dates of the
subordinate WBS elements should lie within the time frame of the
superior WBS element.
The system checks the dates when you save. If there are scheduling
conflicts, you must adjust the dates accordingly.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CJ527
- Endtermin liegt nach Endtermin & des übergeordneten PSP-Elements ?Get instant SAP help. Start your 7-day free trial now.
CJ526
Endtermin liegt nach Endtermin & des Projekts
Was verursacht dieses Problem? The finish date that you entered for the WBS element is later than finish date &V1& in the project definitio...
CJ525
Starttermin liegt vor Starttermin & des Projekts
Was verursacht dieses Problem? The start date that you entered for the WBS element is earlier than start date &V1& in the project definitio...
CJ528
Startermin liegt in der Zukunft
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
CJ529
Endtermin liegt in der Zukunft
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.