Message text: Starttermin liegt vor Starttermin & des übergeordneten PSP-Elements
The start date which you entered for the WBS element is earlier than
start date &V1& for the superior WBS element.
INCLUDE 'NA_ALLG_VERARBEITUNG' OBJECT DOKU ID TX
If you use top-down planning and shift dates, the dates of the
subordinate WBS elements should lie within the time frame of the
superior WBS element.
The system checks the dates when you save. If there are scheduling
conflicts, you must adjust the dates accordingly.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CJ524
- Starttermin liegt vor Starttermin & des übergeordneten PSP-Elements ?Get instant SAP help. Start your 7-day free trial now.
CJ523
Die Vorgangsnummer kann nicht vergeben werden
Was verursacht dieses Problem? The system could not assign a unique number to the activity while you were creating it in a Gantt chart.Systemantwor...
CJ522
Netzplanprofil nicht vorhanden. Bitte Projektdefinition ändern
Was verursacht dieses Problem? You have not entered a network profile in the project definition. The system requires a network profile in order to ...
CJ525
Starttermin liegt vor Starttermin & des Projekts
Was verursacht dieses Problem? The start date that you entered for the WBS element is earlier than start date &V1& in the project definitio...
CJ526
Endtermin liegt nach Endtermin & des Projekts
Was verursacht dieses Problem? The finish date that you entered for the WBS element is later than finish date &V1& in the project definitio...