Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 507
Message text: Starttermin des PSP-Elements & paßt nicht mehr
The start date which you entered for WBS element &V1& does not lie
within the time frame of the superior WBS element any more.
There will be scheduling conflicts if you continue with time scheduling.
INCLUDE 'NA_ALLG_VERARBEITUNG' OBJECT DOKU ID TX
Use the menu option <LS> Edit</> to check and reconcile the dates.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CJ507
- Starttermin des PSP-Elements & paßt nicht mehr ?Get instant SAP help. Start your 7-day free trial now.
CJ506
Endtermin des PSP-Elements & paßt nicht mehr
Was verursacht dieses Problem? The finish date which you entered for WBS element &V1& does not lie within the time frame of the superior WB...
CJ505
PSP-Element & ist für die Terminplanung gesperrt
Was verursacht dieses Problem? WBS element &V1& has the status "locked dates." You cannot maintain any dates.Systemantwort INCL...
CJ508
PSP-Element & hat keine Vorgänge
Was verursacht dieses Problem? WBS element &V1& does not have any activities and therefore also has no dates for comparison.Systemantwort ...
CJ509
Bitte Standardnetz oder Netzplan eingeben
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.