Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 471
Message text: Vorgänge zum PSP-Element & konnten nicht eingelesen werden
The activities for WBS element &V1& can not be read in the project
planning board because they are currently being edited by another user.
INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX
RESET N1
Select the menu options <LS>Extras -> Log -> Lock log - activity</>.
You will receive a log which shows the users and the activities they
are editing (that is, locking).
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CJ471
- Vorgänge zum PSP-Element & konnten nicht eingelesen werden ?Get instant SAP help. Start your 7-day free trial now.
CJ470
========================Projektplantafel=================================
Was verursacht dieses Problem? There is no WBS element for standard WBS element &V1&. The program terminated.Systemantwort INCLUDE '...
CJ469
Wurzelelement der Hierarchie darf nicht verschoben werden
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
CJ472
Bitte Profil für Projektplantafel in Projektprofil & eintragen
Was verursacht dieses Problem? You have not defined a profile for the project planning board in project profile &V1&.Systemantwort INCLUD...
CJ473
Die terminierten Termine können nicht geändert werden
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...