How To Fix CJ441 - Bitte Teilprojektzuordnung vollständig bearbeiten


CJ441 - Overview

  • Message type: E = Error

  • Message class: CJ - Project master data and structure

  • Message number: 441

  • Message text: Bitte Teilprojektzuordnung vollständig bearbeiten

  • Show details Hide details
  • Was verursacht dieses Problem?

    You have assigned individual WBS elements to subprojects; however, you
    must assign <ZH>each</> WBS element to a subproject in order to have an
    accurate evaluation in the project information system.

    Systemantwort

    If you are working with a standard WBS this is only an informational
    message. The system will still save the WBS.
    If you are working with a operative work breakdown structure the system
    will not save the WBS.

    Wie behebe ich diesen Fehler?

    Change the assignments to subprojects. To do this, on the detail
    screens, select the <LS>Organisation</> tab page and either assign
    every WBS element to a subproject or remove the subproject assignment
    from the individual WBS elements.

    Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE


CJ441 - Details








Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Zugehörige SAP-Fehlermeldungen

Klicken Sie auf die Links unten, um die folgenden verwandten Nachrichten anzuzeigen:

Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker