Do you have any question about this error?
Message type: E = Error
Message class: CC - ECM: Messages
Message number: 141
Message text: Änderungsnummer &: & kollidiert mit vorhandenem Änderungsstand
You want to carry out a date shift.
When you carry out a date shift, the system re-defines the valid-from
date for each effectivity period of the objects linked to the change
master.
This process would change the sequence of effectivity periods of BOM
&V2&, alternative &V3& on &V1&.
The system checks whether the BOM is still consistent after a date
shift. This is not the case if, for example, the BOM has already been
changed using a change number with the new valid-from date you want to
shift to.
As the BOM will no longer be consistent if the date shift is carried
out, you cannot carry out the date shift.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CC141
- Änderungsnummer &: & kollidiert mit vorhandenem Änderungsstand ?Get instant SAP help. Start your 7-day free trial now.
CC140
Verbuchungsfehler: Tabelle & Funktion & Returncode &
Was verursacht dieses Problem? Processing (update) of function &V2& was interrupted. No change was made to the database in table &V1&am...
CC139
Revisionsstand & ist nicht maximal
Was verursacht dieses Problem? You want to assign a revision level to a change status of an object (for example, a material). Settings in the "...
CC142
Änderungsnummer &: & verändert Reihenfolge
Was verursacht dieses Problem? You want to carry out a date shift. When you carry out a date shift, the system re-defines the valid-from date for e...
CC143
& & & &
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.