Message type: E = Error
Message class: C7 - Scheduling
Message number: 111
Message text: Bitte prüfen, ob mehrere Planungsebenen sinnvoll -> Langtext beachten
You are attempting to set the <ZH>scheduling</> and/or <ZH>capacity
planning</> indicators for several scheduling levels. Please note the
following:
Because rough-cut, rate-based and detailed planning levels are entirely
different and production orders can only be updated on the detailed
planning level, problems may occur when calculating capacity
requirements.
If you convert a planned order into a production order, only the
detailed planning view is updated when you make changes in the
production order. In detailed planning, the capacity requirements
calculated for rate-based planning are the same as they were for the
last planning status for rate-based scheduling of the planned order.
Setting the indicators for several scheduling levels means that an
order is scheduled at each level which causes a decrease in
performance. If possible, set the indicator for only one scheduling
level.
If you want to schedule on several different levels at the same time,
you have to set the parameters for capacity planning and scheduling in
such a way that only one scheduling level is used to determine the
order basic dates.
If you already set the <ZH>scheduling</> and/or <ZH>capacity
planning</> indicators for
rate-based scheduling and now you want to set them for detailed
scheduling,
rate-based and detailed scheduling and now you want to set them only
for detailed scheduling because of poor performance,
note that all existing planned orders have to be scheduled again at a
later time.
If you would like to have universal planning for production rate
oriented production, you have the following options:
You can use the <ZH>detailed</> scheduling level only. Set the
<ZH>scheduling</> and/or <ZH>capacity planning</> indicators. Then you
can also use rate routings in scheduling.
You can use the detailed and rate-based scheduling levels. You can
determine basic order dates and remove bottlenecks by means of capacity
leveling at the rate-based scheduling level. At the detailed scheduling
level, you should only carry out capacity leveling for the basic order
dates determined by rate-based scheduling. This means you must set the
parameters for detailed scheduling in Customizing in such a way that
the basic order dates are not adjusted.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
C7111
- Bitte prüfen, ob mehrere Planungsebenen sinnvoll -> Langtext beachten ?Get instant SAP help. Start your 7-day free trial now.
C7110
Rahmenendtermin liegt nach dem Bedarfstermin &
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
C7109
Eckendtermin liegt nach dem Bedarfstermin &
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
C7112
Beziehungswissen zu kompliziert. Arbeitsplan & , Folge & , Vorgang &
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
C7118
Terminierung ist noch nicht ausgeführt
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.