How To Fix AP194 - PSP-Element &1 bereits budgetiert oder Verf.kontrolle aktiv


SAP Error Message - Details

  • Message type: E = Error

  • Message class: AP - Investment program messages

  • Message number: 194

  • Message text: PSP-Element &1 bereits budgetiert oder Verf.kontrolle aktiv

  • Show details Hide details
  • Was verursacht dieses Problem?

    You tried to attach WBS element &V1& to a program position. The
    settings for this program position specify that all WBS elements that
    are assigned to it receive their budget solely from this program
    position during budget distribution.
    However, the WBS element &V1& that you are trying to attach already has
    a budget. The budget it has received does <ZH>not</> come from an
    investment program. Or, availability control is still active for the
    WBS element.

    Systemantwort

    In order to avoid inconsistencies, the system does not attach the WBS
    element to the investment program position.

    Wie behebe ich diesen Fehler?

    First reduce to zero all currently existing budget amounts on WBS
    element &V1& (for example, using budget returns). And, if necessary,
    deactivate availability control for the WBS element.
    Then you can attach the WBS element to the program position, and
    distribute budget amounts from the program position to the WBS element.
    following text copied in part from message AP102
    If you want to avoid deactivating availability control, there is
    another option. You can remove 'budgeted' status on the WBS element
    (transaction OPSX).
    To be able to remove 'budgeted' status, you have to reduce the current
    overall and annual budget on the WBS element to zero, and - very
    important - you have to use the <ZH>same</> business transaction
    (original, supplement, return ... ) as was used for entering the
    original budget!
    If the current overall and annual budgets already consist of more than
    one business transaction, then you have to remove each of the budgets
    separately according to the business transaction used. (In order to
    avoid temporary inconsistencies, you should also ideally do this in the
    reverse order to that in which the budget was posted.)
    <ZH>Example</>
    You create a current overall budget as follows:
    RESET N1.
    Original budget 1000
    Supplement 200
    Return 50
    To remove 'budgeted' status from the WBS element, it is not enough to
    enter a return of 1150, for example, even though this would reduce the
    current overall budget to zero.
    Instead you have to reduce the current overall budget to zero in the
    following sequence:
    RESET N1.
    Return 50-
    Supplement 200-
    Set original budget of 1000 to 0.
    You can only remove 'budgeted' status on the WBS element (transaction
    OPSX) after following these steps.

    Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE


Smart SAP Assistant

  • Was ist die Ursache und Lösung für den SAP Fehler AP194 - PSP-Element &1 bereits budgetiert oder Verf.kontrolle aktiv ?




    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Zugehörige SAP-Fehlermeldungen

Klicken Sie auf die Links unten, um die folgenden verwandten Nachrichten anzuzeigen:

Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author