Message type: E = Error
Message class: AO - Appropriation requests - Master data / Customizing
Message number: 611
Message text: Auftrag &1 hat Kalkulation. Planwertübernahme nicht mehr möglich.
An EasyCostPlanning cost estimate was already entered for order &v1&.
It is no longer possible for this order to adopt plan values.
Action is terminated.
Check if the cost estimate on the order should be kept. If not, delete
it. After that it is again possible for the order to adopt plan values
from the appropriation request.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
Get instant SAP help. Sign up for our Free Essentials Plan.
AO610 Variante &1 hat Kalkulation. Planwertübernahme nicht mehr möglich.
Was verursacht dieses Problem? Variant &v1& has a cost estimate. For variants with a cost estimate, it is only possible for measures to ado...
AO609 PSP-Element &1 hat Kalkulation. Planwertübernahme nicht möglich.
Was verursacht dieses Problem? Costing was already entered in the Project Builder for WBS element &v1& . It is not possible to adopt more p...
AO612 Kalkulation nicht gefunden.
Was verursacht dieses Problem? A cost estimate, which is not on the database, is assigned to a variant of the appropriation request.Systemantwort ...
AO613 Realisierungsbeginn &1 außerhalb Planungshorizont &2 - &3.
Was verursacht dieses Problem? Implementation start date &v1& is not within the planning interval from &v2& to &v3&. This i...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.