Do you have any question about this error?
Message type: E = Error
Message class: K8 - CO Planning: Messages for Function Group KAPP
Message number: 138
Message text: Le prix pour la ressource &1 est défini avec différentes devises
The price for resource &V1& has been defined using different
currencies. However, in CO Planning, you are only allowed to use one
currency per fiscal year.
In planning, the R/3 System takes a resource price of zero for the
valuation.
Maintain valid prices for resource &V1& for WBS element &V2&, fiscal
year &V3&, version &V4&, so that the price determination strategy finds
the price in only one currency.
You can analyze the price determination if you activate condition
analysis for the valuation variants used for version &V4& in fiscal
year &V3&.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
K8138
- Le prix pour la ressource &1 est défini avec différentes devises ?Get instant SAP help. Start your 7-day free trial now.
K8137
Le prix pour la ressource &1 est défini avec différentes devises
Quelle est la cause de ce problème? The price for resource &V1& has been defined using different currencies. However, in CO Planning, you a...
K8136
Le prix pour la ressource &1 est défini avec différentes devises
Quelle est la cause de ce problème? The price for resource &V1& has been defined using different currencies. However, in CO Planning, you a...
K8139
L'unité & du prix de recette ou de la qté de recette n'est pas possible
Quelle est la cause de ce problème? You have entered the value &V1& for the unit of the recipe price in CO area- or object currency, or you...
K8140
Le prix de la ressource &1 n'est pas définie dans la période &2.&3.
Quelle est la cause de ce problème? The system cannot determine the resource price.Réponse du système Processing is terminated.Comment corriger ...
Cliquez sur ce lien pour rechercher tous les messages SAP.