How To Fix CN747 - Reprise d'au max. &1 jours en tant que durée de l'activité &2.


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CN - Meldungen für Netzpläne

  • Message number: 747

  • Message text: Reprise d'au max. &1 jours en tant que durée de l'activité &2.

  • Show details Hide details
  • Quelle est la cause de ce problème?

    You want to adjust the duration of a network activity to the maximum
    delivery time or replenishment lead time of all allocated material
    components.

    Réponse du système

    The system only calculates using the allocated material components that
    have the indicator <ZH>Alignment finish date</> set. The maximum
    duration comes from
    the planned delivery time when the material components are procured
    externally
    the total replenishment lead time when the material components are
    produced internally or the in-house production time if the total
    replenishment lead time is not maintained in the material master

    Comment corriger cette erreur?

    Make sure that the <ZH>Alignment finish date</> indicator on the
    component detail screen of the activity is set for all material
    components allocated to the activity.

    Extrait du message d'erreur du système SAP. Copyright SAP SE.


Smart SAP Assistant

  • Quelle est la cause et la solution de l'erreur SAP CN747 - Reprise d'au max. &1 jours en tant que durée de l'activité &2. ?




    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Messages d'erreur SAP associés

Cliquez sur les liens ci-dessous pour voir les messages connexes suivants:

Cliquez sur ce lien pour rechercher tous les messages SAP.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker