Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 061
Message text: Définitions de projet diffèrent dans l'en-tête et l'activité
The network you are editing has account assignment.
The WBS element that you want to assign to an activity has a different
project definition than the one you have entered in the network header.
The WBS element in the activity must have the same project definition as
in the network header.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
RESET N1
Check to make sure that you entered the correct WBS element. If
necessary change your entry.
Check the project definition of the WBS element and change it if
necessary.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
CN061
- Définitions de projet diffèrent dans l'en-tête et l'activité ?Get instant SAP help. Start your 7-day free trial now.
CN060
Affichage des coûts impossible car paramètres manquants
Quelle est la cause de ce problème? The cost display could not be created. An internal error occurred.Réponse du système INCLUDE 'NA_ALLG_N...
CN059
Activité sans coûts
Quelle est la cause de ce problème? No planned costs could be calculated for the activity.Extrait du message d'erreur du système SAP. Copyright SA...
CN062
& Date de fin située dans le passé
Message auto-explicatif Étant donné que SAP estime que ce message d'erreur spécifique est 'auto-explicatif', aucune autre information n'a été fou...
CN063
Le réseau partiel ne peut pas être créé
Quelle est la cause de ce problème? You have not maintained all the parameters in Customizing which are necessary to create a subnetwork.Réponse d...
Cliquez sur ce lien pour rechercher tous les messages SAP.