Do you have any question about this error?
Message type: E = Error
Message class: PJ - MPX interface messages (Download and Upload)
Message number: 650
Message text: La operación & está definida dos veces (verifíquelo)
The MPX files have the same name several times for the same field
<ZH>Text10</>. The project system creates the activity number from
<ZH>Text10</> during upload.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Check in Microsoft Project (R) the names you have used for <ZH>Text
10</> and make any changes necessary.
Please note:
The numbers for the activity elements in a standard network may not be
identical to each other or to the activity numbers (field
<ZH>Text10</>).
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
PJ650
- La operación & está definida dos veces (verifíquelo) ?Get instant SAP help. Start your 7-day free trial now.
PJ640
Operación &: el recurso & asignado no está definido (verifíquelo)
¿Qué causa este problema? You have defined resources for an activity that do not exist in Microsoft Project (R).Respuesta del sistema INCLUDE ...
PJ630
Error al leer el fichero PC (verifique el PC)
¿Qué causa este problema? An error occurred while reading the MPX file from the PC.Respuesta del sistema INCLUDE 'NA_ALLG_NOFUNKTION' OB...
PJ660
El elemento de operación & está definido dos veces (verifíquelo)
¿Qué causa este problema? The MPX files has the same name several time for the same field <ZH>Activity notes</>. The project system cre...
PJ670
El puesto de trabajo & está definido dos veces (verifíquelo)
¿Qué causa este problema? The MPX files has the same name several time for the same field <ZH>Short text</>. The project system creates...
Haga clic en este enlace para buscar todos los mensajes de SAP.