Do you have any question about this error?
Message type: E = Error
Message class: MPE_INSTALLATION_MSG -
Message number: 036
Message text: Componente no asignado a la actividad
Why is it relevant?
Every demand for an installation kit should be assigned to a network
activity to define the sequence in which installation kits shall be
assembled.
Possible reasons:
This could be a bug in the bill of material transfer (transaction CN33,
CN33_N).
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Fix:
Re-explode the current BOM version either in this app or using
transaction CN33_N.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
MPE_INSTALLATION_MSG036
- Componente no asignado a la actividad ?Get instant SAP help. Start your 7-day free trial now.
MPE_INSTALLATION_MSG035
Componente asignado a la actividad con un punto de referencia incorrecto
¿Qué causa este problema? One of the following applies: The production engineer manually assigned the component to an individually selected network...
MPE_INSTALLATION_MSG034
Componente asignado a actividad sin punto de referencia
¿Qué causa este problema? You manually assigned the BOM item to a network activity or you created the network directly from the BOM.Respuesta del s...
MPE_INSTALLATION_MSG037
La actividad referenciada no existe
¿Qué causa este problema? Why is it relevant? Every demand for an installation kit should be assigned to a network activity to define the sequence ...
MPE_INSTALLATION_MSG038
Componente asignado a actividad sin punto de referencia
¿Qué causa este problema? Why is it relevant The advantage of using reference points is that you do not have to manually assign BOM items to networ...
Haga clic en este enlace para buscar todos los mensajes de SAP.