Do you have any question about this error?
Message type: E = Error
Message class: KP - CO-OM Planning
Message number: 246
Message text: CeCo & clase de actividad &: Actividad = 0.
Activity planning in periods &V3& is not reconciled for cost center
&V1&, activity type &V2&. The plan activity of activity type &V2& is 0.
However, a receiver cost center was planned to use this activity
(scheduled activity).
The SAP System cannot calculate the activity price as this would
involve dividing by zero. In order to prevent subsequent errors and to
calculate the activity prices, the SAP System uses scheduled quantity
as activity quantity. Because this is a serious error, the SAP System
does not update the results.
Check planning for activity type &V2& in cost center &V1& and the
activity scheduled for period(s) &V3&.
<DS:TRAN.KP26>Activity Type Planning</>
<DS:TRAN.KP36>Secondary Cost Planning</>
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
KP246
- CeCo & clase de actividad &: Actividad = 0. ?Get instant SAP help. Start your 7-day free trial now.
KP245
CeCo & clase de actividad & actividad < previstos
¿Qué causa este problema? Plan activity in period(s) &V3& is not reconciled for cost center &V1&, activity type &V2&. The p...
KP244
El período & no está previsto.
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
KP247
CeCo & clase de actividad &: La tarifa política fluctúa.
¿Qué causa este problema? You determined a manually-entered activity price for cost center &V1&, activity type &V2&. An annual acti...
KP248
La actualización no se inicia debido a un error.
¿Qué causa este problema? A serious error occurred during processing.Respuesta del sistema Processing is continued as far as possible. However, th...