Message type: E = Error
Message class: GPD - Pegging & Distribution
Message number: 075
Message text: Plan cobertura necesidades &1 no se ha podido asignar completamente
Object &V1& could not be fully assigned.
Processing continues, however the object is not considered during cost
distribution.
In transaction <ZH>PEG06</>, check whether a higher level production
order exists with a goods receipt quantity of zero and an active final
delivery indicator.
Other possible causes may be program error or a process that is not
supported.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
Get instant SAP help. Sign up for our Free Essentials Plan.
GPD074
El status no permite distribución de costes: &1
¿Qué causa este problema? The object status does not permit cost postings. Examples of such statuses are 'opened' and 'completed...
GPD073
Imposible anular elemento PEP planif.necesidades distribución costes &1
¿Qué causa este problema? Problems occured when cancelling the cost distribution for grouping WBS element &V1&: The selected period does no...
GPD076
Orden de renovación &: Asignación basada en historial de orden &
¿Qué causa este problema? Assignment of refurbishment order &V1& is based on the history of order &V2&. Order &V1& was trig...
GPD077
Conjunto &, orden & tiene nivel planif.nec.menor o igual que material &
¿Qué causa este problema? Assignment of order &V2& is based on the historical assignments of material &V1&. The pegging process dep...