Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 345
Message text: El grafo &/&: la fecha de fin difiere de la fecha de limitación
The start date for the operation has the constraint that it should
finish on a particular date (constraint date). However the start date
when you want to dispatch the operation leads to a finish date which
does not correspond to the constraint date. So it is not possible to
dispatch the operation.
You should change the start date on which you want to dispatch the
operation.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
CY345
- El grafo &/&: la fecha de fin difiere de la fecha de limitación ?Get instant SAP help. Start your 7-day free trial now.
CY344
El grafo &/&: la fecha de inico es posterior a fecha de limitación
¿Qué causa este problema? The start date for the operation has the constraint that it should not be after a particular date (constraint date). Howe...
CY343
El grafo &/&: la fecha de incio es anterior a fecha de limitación
¿Qué causa este problema? The start date for the operation has the constraint that it should not be before a particular date (constraint date). How...
CY346
El grafo &/&: la fecha de fin es anterior a la fecha de limitación
¿Qué causa este problema? The finish date for the operation has the constraint that it should not be before a particular date (constraint date). Ho...
CY347
El grafo &/&: la fecha de fin es posterior a la fecha de limitación
¿Qué causa este problema? The finish date for the operation has the constraint that it should not finish after a particular date (constraint date)....