Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 524
Message text: La fecha inicio es anterior a fecha inicio & del elemento PEP superior
The start date which you entered for the WBS element is earlier than
start date &V1& for the superior WBS element.
INCLUDE 'NA_ALLG_VERARBEITUNG' OBJECT DOKU ID TX
If you use top-down planning and shift dates, the dates of the
subordinate WBS elements should lie within the time frame of the
superior WBS element.
The system checks the dates when you save. If there are scheduling
conflicts, you must adjust the dates accordingly.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
CJ524
- La fecha inicio es anterior a fecha inicio & del elemento PEP superior ?Get instant SAP help. Start your 7-day free trial now.
CJ523
El número de la operación no se puede asignar
¿Qué causa este problema? The system could not assign a unique number to the activity while you were creating it in a Gantt chart.Respuesta del sis...
CJ522
Perfil de grafo no existe. Modifique la definición del proyecto
¿Qué causa este problema? You have not entered a network profile in the project definition. The system requires a network profile in order to sched...
CJ525
La fecha inicio es anterior a fecha inicio & del proyecto
¿Qué causa este problema? The start date that you entered for the WBS element is earlier than start date &V1& in the project definition.Res...
CJ526
La fecha fin es posterior a fecha fin & del proyecto
¿Qué causa este problema? The finish date that you entered for the WBS element is later than finish date &V1& in the project definition.Res...