Message text: The work center &1 / plant &2 is not in the active integration model
The work center of resource &V1& in plant &V2& does not exist in an
active integration model or a work center has not been entered in the
operation/phase.
For the order transfer, the system assumes that the work center will
not be planned in the connected APO system. Operations/phases that are
to be processed at this work center are not sent to the APO system.
Operations/phases that are not assigned to a work center are also not
transferred to the APO system.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Internal key of the work center:
ARBID: &V3&
Error message extract from SAP system. Copyright SAP SE.
X4502
- The work center &1 / plant &2 is not in the active integration model ?The SAP error message X4502 indicates that a specific work center in a particular plant is not included in the active integration model. This error typically arises in the context of SAP's integration with other systems, such as SAP S/4HANA or SAP ERP, particularly when dealing with Master Data Management or when using the SAP Integration Model for data replication.
Cause:
- Missing Work Center in Integration Model: The work center and plant combination you are trying to use is not part of the active integration model. This means that the system does not recognize this work center as valid for the current integration scenario.
- Inactive Integration Model: The integration model that includes the work center may not be activated or may not be the one currently in use.
- Data Replication Issues: If you are trying to replicate data from one system to another, the work center may not have been included in the data replication setup.
Solution:
Check Integration Model:
- Go to the transaction code
CPI1
(for displaying integration models) orCPI2
(for changing integration models).- Verify if the work center and plant combination is included in the active integration model.
- If it is not included, you will need to add it to the integration model.
Activate Integration Model:
- If the integration model is not active, activate it using transaction code
CPI1
orCPI2
.- Ensure that the model is correctly configured to include all necessary work centers and plants.
Replicate Data:
- If you are working with data replication, ensure that the work center is included in the data replication setup.
- Use transaction code
CPI1
to check the settings and ensure that the work center is part of the replication process.Check for Authorizations:
- Ensure that you have the necessary authorizations to view and modify the integration model.
Consult Documentation:
- Review SAP documentation or help resources for specific details related to your version of SAP and the integration model you are using.
Related Information:
CPI1
, CPI2
, and CPI3
for managing integration models.If the issue persists after following these steps, it may be beneficial to consult with your SAP Basis or technical team for further investigation, as there may be underlying configuration issues or system-specific settings that need to be addressed.
Get instant SAP help. Start your 7-day free trial now.
X4501
Relationships for order &1 cannot be redirected
What causes this issue? In process order &V1& phases are missing for the transfer to APO. The system has attempted to divert the relationship...
X4500
*** APO-specific outbound messages ***
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
X4503
Control key &1 not relevant to scheduling or is a rework operation
What causes this issue? The control key &V1& entered in the operation or the phase indicates that the operation is not relevant to scheduling...
X4504
Operation/phase with duration zero
What causes this issue? The operation or the phase has no duration.System Response Operations/phases that have no duration are not transferred to th...