How To Fix V4328 - JIT delivery schedule horizon not created for item &1


SAP Error Message - Details

  • Message type: E = Error

  • Message class: V4 - Nachrichten Verkauf (Variable Meldungen und EDI-Meldungen)

  • Message number: 328

  • Message text: JIT delivery schedule horizon not created for item &1

  • Show details Hide details
  • What causes this issue?

    You changed or created a JIT delivery schedule for item &V1& in a
    delivery schedule with an external service agent, without filling the
    the JIT delivery schedule horizon. This is a mandatory field.
    For a delivery schedule with an external service agent, the JIT
    delivery schedule horizon cannot be seen on the scheduling screen, but
    only on the delivery schedule header.

    System Response

    The system does not allow you to save a delivery schedule with JIT
    delivery schedules or a JIT delivery schedule horizon to avoid unwanted
    effects on requirements.

    How to fix this error?

    Branch to the delivery schedule header for the JIT delivery schedule
    for item &V1&. Create the JIT delivery schedule horizon.
    It is now possible to save the delivery schedule.

    Procedure for System Administrators

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message V4328 - JIT delivery schedule horizon not created for item &1 ?

    The SAP error message V4328 indicates that a Just-In-Time (JIT) delivery schedule horizon has not been created for a specific item in the system. This error typically arises in the context of JIT delivery scheduling, which is used in manufacturing and supply chain management to ensure that materials are delivered just in time for production.

    Cause:

    The error can occur due to several reasons, including:

    1. Missing Configuration: The JIT delivery schedule may not be properly configured in the system for the specific material or item.
    2. Incorrect Master Data: The material master or vendor master data may be incomplete or incorrect, leading to the inability to create a JIT delivery schedule.
    3. Scheduling Parameters: The scheduling parameters for the JIT delivery may not be set correctly, such as lead times or delivery dates.
    4. Lack of JIT Agreement: There may not be a valid JIT agreement in place for the item, which is necessary for creating delivery schedules.
    5. Item Not Relevant for JIT: The item in question may not be set up to be relevant for JIT delivery in the system.

    Solution:

    To resolve the V4328 error, you can take the following steps:

    1. Check JIT Configuration:

      • Ensure that the JIT delivery schedule is configured correctly in the system. This includes checking the relevant customizing settings in SPRO (SAP Project Reference Object).
    2. Review Material Master Data:

      • Verify that the material master data for the item is complete and correctly maintained. Check the JIT-related fields in the material master.
    3. Examine Vendor Master Data:

      • Ensure that the vendor master data is also complete and that the vendor is set up for JIT delivery.
    4. Check Scheduling Parameters:

      • Review the scheduling parameters for the item, including lead times, delivery dates, and any other relevant settings.
    5. Validate JIT Agreement:

      • Confirm that there is a valid JIT agreement in place for the item. If not, you may need to create or update the agreement.
    6. Consult Documentation:

      • Refer to SAP documentation or help resources for specific details on JIT delivery scheduling and any additional configuration that may be required.
    7. Contact Support:

      • If the issue persists after checking the above points, consider reaching out to your SAP support team or consulting with an SAP expert for further assistance.

    Related Information:

    • Transaction Codes: You may need to use transaction codes such as ME31K (Create JIT Delivery Schedule) or ME32K (Change JIT Delivery Schedule) to manage JIT schedules.
    • SAP Notes: Check for any relevant SAP Notes that may address known issues or provide additional guidance related to JIT delivery scheduling.
    • Training and Documentation: Ensure that users involved in JIT processes are adequately trained and have access to documentation regarding JIT delivery scheduling in SAP.

    By following these steps, you should be able to identify the root cause of the V4328 error and implement the necessary solutions to resolve it.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant