How To Fix RU211 - Enter either forecast finish or forecast duration


SAP Error Message - Details

  • Message type: E = Error

  • Message class: RU - Messages for order completion confirmation

  • Message number: 211

  • Message text: Enter either forecast finish or forecast duration

  • Show details Hide details
  • What causes this issue?

    You have entered a finish date <ZH>and</> a duration for the forecast
    completion confirmation. This is not possible.

    System Response

    INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX

    How to fix this error?

    Enter either a date or a duration.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message RU211 - Enter either forecast finish or forecast duration ?

    The SAP error message RU211, which states "Enter either forecast finish or forecast duration," typically occurs in the context of project management or production planning within SAP. This error indicates that the system requires either a forecast finish date or a forecast duration to proceed with the operation you are attempting to perform.

    Cause:

    The error arises when:

    • You are trying to create or update a project, task, or production order without providing the necessary forecast information.
    • The system needs either a specific finish date for the forecast or the duration of the forecast to calculate timelines and resource allocations.

    Solution:

    To resolve the RU211 error, you can take the following steps:

    1. Enter Forecast Finish Date:

      • Navigate to the relevant screen where you are entering project or production details.
      • Look for the field labeled "Forecast Finish" and enter a valid date that indicates when you expect the project or task to be completed.
    2. Enter Forecast Duration:

      • Alternatively, you can provide a forecast duration instead of a finish date.
      • Find the field for "Forecast Duration" and enter the expected duration of the task or project in the appropriate unit (e.g., days, hours).
    3. Check Required Fields:

      • Ensure that all mandatory fields are filled out correctly. Sometimes, other related fields may also need to be completed to avoid errors.
    4. Review Configuration:

      • If you are consistently encountering this error, it may be worth reviewing the configuration settings in your SAP system to ensure that the forecast parameters are set up correctly.
    5. Consult Documentation:

      • Refer to SAP documentation or help resources for specific guidance related to the transaction or module you are working with.
    6. Seek Help from SAP Support:

      • If the issue persists, consider reaching out to your SAP support team or consulting SAP Notes for any known issues or patches related to this error.

    Related Information:

    • Transaction Codes: The error may occur in various transaction codes related to project management (e.g., CJ20N for Project Builder) or production planning (e.g., CO01 for creating production orders).
    • SAP Modules: This error is often encountered in modules like SAP Project System (PS) and SAP Production Planning (PP).
    • User Roles: Ensure that you have the necessary permissions to enter forecast data in the system.

    By following these steps, you should be able to resolve the RU211 error and proceed with your project or production planning activities in SAP.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author