Message type: E = Error
Message class: RSH_LEVELING - Leveling Relevant Messages
Message number: 030
Message text: Your change couldn't be completed. Schedule status has changed.
Another planner has changed the schedule status. The change you wanted
to make is not possible with the new schedule status.
For example, if another planner has gone from <LS>Refinement</> back to
<LS>Scoping</> after you selected an operation for manual scheduling,
you can no longer set a start day for an operation.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Still want to make the change? If required, change the schedule
status and try again:
To change from <LS>Refinement</> to <LS>Scoping</>, click <Ls>Go Back to
Scoping</>.
To change from <LS>Scoping</> to <LS>Refinement</>, click <LS>Refine
Schedule</>.
Error message extract from SAP system. Copyright SAP SE.
RSH_LEVELING030
- Your change couldn't be completed. Schedule status has changed. ?The SAP error message RSH_LEVELING030 indicates that a change you attempted to make in the scheduling of a project or task could not be completed because the schedule status has changed. This typically occurs in the context of project management or production planning within SAP, particularly when dealing with scheduling and leveling of resources. Causes: Status Change: The schedule status of the project or task may have changed due to another user’s actions or system processes, making your change invalid. Locking Issues: The object you are trying to modify may be locked by another user or process, preventing your changes from being applied. Dependencies: There may be dependencies or constraints that prevent the change from being executed. Data Inconsistencies: There could be inconsistencies in the data that need to be resolved before changes can be made. Solutions: Refresh the Data: Refresh the screen or re-fetch the data to ensure you are working with the most current information.
Get instant SAP help. Sign up for our Free Essentials Plan.
RSH_LEVELING029
Someone has made changes to the schedule. Please refresh and try again.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
RSH_LEVELING028
You've shared the schedule with &1 persons.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
RSH_LEVELING031
Schedule &1 includes work centers that are not assigned to you.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
RSH_LEVELING032
The schedule includes work centers that are not assigned to you.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.