Message type: E = Error
Message class: PK - Production - KANBAN
Message number: 460
Message text: Creation of several planned orders with one action is not possible
According to your settings, the system is to create several planned
orders in one posting step. However, this is not possible for technical
reasons. The reasons for this behaviour could include:
You defined in the control cycle that the rounding quantity is a real,
integral multiple of the fixed kanban quantity.
When creating the event-driven kanbans, you entered a quantity that is a
real, integral multiple of the fixed kanban quantity.
In the replenishment strategy, you defined that a load carrier
corresponds to a kanban and when creating the event-driven kanbans, you
entered several load carriers.
This results in several kanbans and therefore several planned orders
being created in one step.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Set the system so that when using the replenishment strategy <LS>Process
with Planned Orders/Planning with MRP</>, only one kanban is created
per posting step and, therefore, only one planned order per posting step
is created.
Error message extract from SAP system. Copyright SAP SE.
PK460
- Creation of several planned orders with one action is not possible ?The SAP error message PK460, which states "Creation of several planned orders with one action is not possible," typically occurs in the context of production planning and scheduling within the SAP system. This error indicates that the system is unable to create multiple planned orders simultaneously due to certain constraints or settings. Causes: Configuration Settings: The system may be configured to allow only single planned order creation for certain materials or production processes. Batch Management: If the material is batch-managed, the system may restrict the creation of multiple planned orders to ensure proper batch handling. Order Type Restrictions: Certain order types may have restrictions that prevent the creation of multiple planned orders at once. Material Availability: If there are issues with material availability or other prerequisites, the system may not allow multiple planned orders to be created. User Authorizations: The user may not have the necessary authorizations to create multiple planned orders. Solutions: Check Configuration: Review the configuration
Get instant SAP help. Sign up for our Free Essentials Plan.
PK459
Dependent requirement on &1 for material &2 does not lie on workday
What causes this issue? For material &v2&, the dependent requirement of &v1&, which is to be used for the kanban calculation, does no...
PK458
Distribute correction quantity to quants
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PK461
Synchronous confirmation of production order without bin is not possible
What causes this issue? The production order &V3& shall synchronously post goods receipt for material &V2& into inventory management ...
PK462
Select "Save" to post the summarized JIT call
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.