Message type: E = Error
Message class: MPE_INSTALLATION_MSG -
Message number: 039
Message text: Component assigned to activity with wrong reference point
Why is it relevant?
Reference points serve the assignment of BOM items to network
activities. The component demand (reservation) is assigned to a
different network activity than what is defined by the reference points.
Possible Reasons:
Production engineer manually assigned the component to an individually
selected network activity in BOM transfer (transaction CN33_N)
or
Reference point in network activity was changed after BOM transfer
or
Reference point in BOM item was changed after BOM transfer
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Fix:
Accept warning
or
Change reference point either in BOM item or network activity (app
?Manage Bill of Material? with item selected or transaction CJ20N with
network activity selected). Subsequently re-explode current BOM version
or
Assign component to a different network activity just by re-exploding
current BOM version
Error message extract from SAP system. Copyright SAP SE.
MPE_INSTALLATION_MSG039
- Component assigned to activity with wrong reference point ?The SAP error message MPE_INSTALLATION_MSG039 indicates that there is a problem with the assignment of a component to an activity in the context of a project or maintenance plan. Specifically, it suggests that the component is assigned to an activity that has an incorrect reference point, which can lead to issues in planning, execution, or reporting.
Cause: Incorrect Configuration: The component may not be properly configured in relation to the activity or project. This could be due to incorrect settings in the master data or project structure. Reference Point Mismatch: The reference point for the component may not align with the reference point expected by the activity. This could happen if the component is intended for a different type of activity or project. Data Inconsistencies: There may be inconsistencies in the data related to the component or activity, such as missing or incorrect entries in the relevant tables.
Solution: Check Configuration: Review the configuration settings for
Get instant SAP help. Sign up for our Free Essentials Plan.
MPE_INSTALLATION_MSG038
Component assigned to activity without reference point
What causes this issue? Why is it relevant The advantage of using reference points is that you do not have to manually assign BOM items to network ac...
MPE_INSTALLATION_MSG037
Referenced activity does not exist
What causes this issue? Why is it relevant? Every demand for an installation kit should be assigned to a network activity to define the sequence in w...
MPE_INSTALLATION_MSG040
Duration in network activity & and material master & differs
What causes this issue? The network and material master have been created independently.System Response This app allows to create network activities...
MPE_INSTALLATION_MSG041
Zero duration in network activity
What causes this issue? The network activity?s duration is not defined.System Response The network activity?s duration represents the time needed to...
Click on this link to search all SAP messages.