Message type: E = Error
Message class: MA - Sales and Operations Planning
Message number: 538
Message text: This PG is not the MRP-relevant PG for all members
You want to pass on product group member data to Demand Management.
However, the product group you have specified is not the MRP-relevant
product group for all materials.
A material typically has an MRP-relevant indicator if it is a member of
more than one product group. You set this indicator in the product
group from which you want the material to be transferred to Demand
Management. This prevents planning data for the same material from
being transferred to Demand Management multiple times from different
product groups.
Transfer materials to Demand Management from their MRP-relevant product
groups.
Error message extract from SAP system. Copyright SAP SE.
MA538
- This PG is not the MRP-relevant PG for all members ?The SAP error message MA538, which states "This PG is not the MRP-relevant PG for all members," typically occurs in the context of Material Requirements Planning (MRP) when dealing with planning groups (PG) in SAP. This error indicates that the planning group assigned to a material is not relevant for MRP processing for all the members of a particular planning group.
Cause:
- Incorrect Planning Group Assignment: The planning group assigned to the material may not be set up correctly or may not be relevant for MRP processing.
- Inconsistent Data: There may be inconsistencies in the master data for the materials involved, such as different planning groups assigned to different members of a product structure (e.g., BOM).
- Configuration Issues: The configuration settings for MRP may not align with the planning group settings, leading to this error.
Solution:
Check Planning Group Assignment:
- Go to the material master data (transaction code MM03) and check the planning group assigned to the material.
- Ensure that the planning group is correctly assigned and is relevant for MRP.
Review MRP Settings:
- Check the MRP settings in the configuration (transaction code OMD0) to ensure that the planning group is set up correctly for MRP processing.
- Verify that the planning group is marked as MRP-relevant.
Consistency Check:
- Ensure that all members of the product structure (e.g., BOM components) have the same planning group assigned if they are supposed to be part of the same MRP run.
- If there are discrepancies, update the planning group for the relevant materials.
Use Transaction Codes:
- Use transaction codes like CS03 (Display BOM) to check the BOM structure and ensure that all components have the correct planning group.
- Use transaction code MD02 (MRP Run) to re-run the MRP after making necessary adjustments.
Consult Documentation:
- Review SAP documentation or help files related to MRP and planning groups for additional insights and best practices.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with an SAP functional consultant or support team for further assistance.
Get instant SAP help. Start your 7-day free trial now.
MA537
Planning version to be transferred is not the active version
What causes this issue? You want to pass on material data to Demand Management: either directly from that material or as a proportion of the product ...
MA536
PG/mat. & in plant & version & - version not found
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MA539
Choose at least one product group member
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MA540
Choose one form of disaggregation
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.