Do you have any question about this error?
Message type: E = Error
Message class: LOG_TRM_INTEGRATION - General message class for Logistic to Treasury Integration
Message number: 013
Message text: The start date of the RDP's validity must not be later than the end date
The validity period of the risk distribution plan in contract item &V3&
is not correct. The start date &V1& must not be later than the end date
&V2&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Open the maintenance screen for the risk distribution plan and correct
the validity period.
Error message extract from SAP system. Copyright SAP SE.
LOG_TRM_INTEGRATION013
- The start date of the RDP's validity must not be later than the end date ?The SAP error message LOG_TRM_INTEGRATION013 indicates that there is an issue with the validity dates of a Risk Data Provider (RDP) in the context of SAP's Risk Management or similar modules. Specifically, the error states that the start date of the RDP's validity must not be later than the end date. This typically occurs when the dates entered for the RDP are not in the correct order.
Cause:
- Incorrect Date Entry: The start date for the RDP has been entered as a date that is later than the end date.
- Data Migration Issues: If data has been migrated from another system, there may be inconsistencies in the date formats or values.
- User Input Error: A user may have mistakenly entered the dates in the wrong fields or swapped them.
Solution:
To resolve this error, follow these steps:
Check the Dates:
- Navigate to the RDP configuration or the relevant transaction where the dates are set.
- Verify the start date and end date fields to ensure that the start date is earlier than or equal to the end date.
Correct the Dates:
- If the start date is indeed later than the end date, correct the dates accordingly.
- Ensure that the format of the dates is consistent with the system's requirements (e.g., DD/MM/YYYY or MM/DD/YYYY).
Save Changes:
- After making the necessary corrections, save the changes and check if the error persists.
Validation:
- If applicable, run any validation checks or tests to ensure that the RDP is functioning correctly after the changes.
Related Information:
If the problem persists after following these steps, it may be beneficial to consult with your SAP support team or a technical consultant who can provide further assistance.
Get instant SAP help. Start your 7-day free trial now.
LOG_TRM_INTEGRATION012
The total quantity in the RDP in contract item &1 is not correct
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
LOG_TRM_INTEGRATION011
The validity period of the RDP in contract item &1 is not correct
What causes this issue? The validity period in the risk distribution plan for contract item &V1& does not match the validity period in the co...
LOG_TRM_INTEGRATION014
The start date of the validity period must not be later than the end date
What causes this issue? The start date &V1& of the validity period of a risk distribution plan item must not be later than the end date &...
LOG_TRM_INTEGRATION015
The start date of an RDP item is earlier than the start date of the RDP
What causes this issue? The start date &V1& of an RDP item is earlier than the start date of the RDP itself &V2&.System Response The...
Click on this link to search all SAP messages.