Message type: E = Error
Message class: KPN - Costing: Networks, Projects
Message number: 026
Message text: Asynchronous costing not possible for network &
Network &V1& is header-assigned. You cannot use the asynchronous
network costing for header-assigned networks.
No costs were determined for network &V1&.
You determine costs for header-assigned networks using network
maintenance, structure maintenance, or the project planning board by
choosing <LS>Edit -> Costs -> Determine costs</> or <LS>Edit ->
Functions -> Determine cost</>.
Error message extract from SAP system. Copyright SAP SE.
KPN026
- Asynchronous costing not possible for network & ?The SAP error message KPN026, which states "Asynchronous costing not possible for network &," typically occurs in the context of project systems or production planning when the system is unable to perform asynchronous costing for a network due to certain conditions not being met.
Cause: Network Structure Issues: The network may not be properly structured or may have missing components, such as activities or relationships. Costing Variant Configuration: The costing variant used may not be configured to allow asynchronous costing. Status of the Network: The network or its activities may be in a status that does not allow costing (e.g., if the network is locked or not released). Missing Master Data: Required master data (like cost centers, activity types, etc.) may be missing or incorrectly configured. System Settings: The system settings for costing may not be correctly set up to allow asynchronous processing.
Solution: Check Network Structure: Ensure that the network is correctly structured with all necessary activities
Get instant SAP help. Sign up for our Free Essentials Plan.
KPN025
Version & does not exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
KPN024
Material component &1 is not costing relevant
What causes this issue? Material component &V1& is not costing relevant. You control the costing relevance of a material component using the ...
KPN027
Select a network or project definition
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
KPN028
There is already an invoicing plan for activity &
What causes this issue? There is already an invoicing plan for activity &V1&. You cannot create a unit costing and an invoicing plan simultan...
Click on this link to search all SAP messages.