How To Fix KPN008 - Activity & could not be valuated by schedule


SAP Error Message - Details

  • Message type: E = Error

  • Message class: KPN - Costing: Networks, Projects

  • Message number: 008

  • Message text: Activity & could not be valuated by schedule

  • Show details Hide details
  • What causes this issue?

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    An internal error has occurred.

    System Response

    Costing by schedule was not possible for this activity. This may be due
    to an error in scheduling or failure to maintain the capacity
    requirement distribution key.
    In the case of internally-processed activities, valuation is at the
    rate for the first period; planned costs are distributed over the whole
    duration of the activity. Distribution keys entered in the activity or
    the work center are ignored.

    How to fix this error?

    Schedule the order again or make sure that the capacity requirement
    distribution key is correctly maintained.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message KPN008 - Activity & could not be valuated by schedule ?

    The SAP error message KPN008 ("Activity & could not be valuated by schedule") typically occurs in the context of controlling and project management within SAP, particularly when dealing with activity types and their valuation in cost planning or project scheduling.

    Cause:

    The error usually arises due to one or more of the following reasons:

    1. Missing Activity Type Valuation: The activity type that is being referenced does not have a valid valuation set up in the system. This could mean that the activity type is not assigned a cost center or that the valuation method is not defined.

    2. Incorrect Configuration: There may be issues with the configuration of the controlling area, activity types, or the related cost centers. If the configuration is not aligned with the requirements of the project or activity, it can lead to this error.

    3. Data Inconsistencies: There might be inconsistencies in the master data related to the activity type, such as missing or incorrect entries in the activity type master data or cost center master data.

    4. Scheduling Issues: If the scheduling of the activity is not properly set up, it may lead to the system being unable to determine the costs associated with the activity.

    Solution:

    To resolve the KPN008 error, you can take the following steps:

    1. Check Activity Type Configuration:

      • Go to the configuration settings for activity types in SAP (Transaction code: OAYD or OAYC).
      • Ensure that the activity type is properly defined and has a valid valuation method assigned.
    2. Validate Cost Center Assignment:

      • Ensure that the activity type is assigned to a valid cost center.
      • Check if the cost center is active and correctly configured.
    3. Review Master Data:

      • Check the master data for the activity type and cost center to ensure that all necessary fields are filled out correctly.
      • Look for any inconsistencies or missing data that could be causing the issue.
    4. Check Scheduling Settings:

      • Review the scheduling settings for the project or activity to ensure that they are correctly configured.
      • Make sure that the activity is scheduled properly and that all dependencies are met.
    5. Consult Documentation:

      • Refer to SAP documentation or help resources for specific guidance on the error message and related configuration settings.
    6. Testing:

      • After making changes, test the activity valuation again to see if the error persists.

    Related Information:

    • Transaction Codes: Familiarize yourself with relevant transaction codes such as OAYD (Activity Type) and OAYC (Activity Type Configuration).
    • SAP Notes: Check SAP Notes for any known issues or patches related to this error message.
    • User Forums: Engage with SAP community forums or user groups for additional insights and solutions from other users who may have encountered the same issue.

    If the problem persists after following these steps, it may be beneficial to consult with an SAP expert or your organization's SAP support team for further assistance.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker