Do you have any question about this error?
Message type: E = Error
Message class: KK -
Message number: 748
Message text: Mixed cost estimate in explosion level &1 for material &2 plant &3
The material cost estimate is to be exploded in explosion level &v1&
for a mixed cost estimate (material &v2& plant &v3&). However, material
explosion does not support the explosion of a mixed cost estimate.
The material cost estimate is not exploded.
The maximum explosion level is indicated in the last logged message for
material explosion. Material explosion can only be performed up to this
level.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
KK748
- Mixed cost estimate in explosion level &1 for material &2 plant &3 ?The SAP error message KK748 indicates that there is a mixed cost estimate in the explosion level for a specific material in a particular plant. This error typically arises during the cost estimate process, particularly when dealing with materials that have different costing methods or when there are inconsistencies in the cost estimates.
Cause:
- Mixed Costing: The error usually occurs when a material has been assigned different costing methods (e.g., standard costing and moving average costing) and the system is unable to reconcile these methods at the specified explosion level.
- Costing Variants: The costing variant used may not be set up correctly to handle mixed costs.
- Material Master Data: There may be inconsistencies or missing data in the material master records, such as the costing view or valuation class.
- Costing Run Configuration: The configuration for the costing run may not be set up to handle mixed cost estimates properly.
Solution:
- Check Material Master: Review the material master data for the affected material. Ensure that the costing views are correctly maintained and that there are no inconsistencies in the valuation class or costing method.
- Review Costing Variant: Check the costing variant settings in the configuration. Ensure that it is set up to handle mixed costing if applicable.
- Costing Run Settings: Verify the settings for the costing run. Ensure that the parameters allow for mixed cost estimates if that is the intended approach.
- Recreate Cost Estimate: If necessary, try to recreate the cost estimate for the material. This may involve resetting the cost estimate and running it again to see if the error persists.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on handling mixed cost estimates and the relevant configuration settings.
Related Information:
By following these steps, you should be able to identify the root cause of the KK748 error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
KK747
There is no plant &2 in controlling area &1
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
KK746
No overhead costs were calculated
What causes this issue? The itemization does not contain any overhead costs because neither overhead rates nor process costs were calculated. Possibl...
KK749
Mixed cost estimate exists: maximum of &1 explosion level(s) possible
What causes this issue? The material cost estimate is to be exploded for one or more mixed cost estimates. However, material explosion does not suppo...
KK750
***** Messages for Where-Used List of Base Planning Objects ******
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.