Message type: E = Error
Message class: KI -
Message number: 344
Message text: Do not use cost element &1 for &2
You made an account assignment with cost element &V1&. In controlling
area &V4& this cost element has type &V4&.
Cost elements of this type cannot be posted in transaction &V2&.
Use a different cost element or check the cost element type.
Error message extract from SAP system. Copyright SAP SE.
KI344
- Do not use cost element &1 for &2 ?The SAP error message KI344 ("Do not use cost element &1 for &2") typically occurs in the context of controlling (CO) when you are trying to post costs to a cost element that is not allowed for a specific cost object or cost center. This error is a safeguard to ensure that only appropriate cost elements are used for certain types of postings.
Cause: Cost Element Configuration: The cost element you are trying to use may not be configured for the specific cost object (e.g., cost center, internal order, etc.) you are posting to. Cost Element Type: The cost element might be of a type that is not permitted for the type of posting you are attempting (e.g., primary vs. secondary cost elements). Cost Center Assignment: The cost center or cost object may not be assigned to the cost element in the configuration settings. Posting Type Restrictions: There may be restrictions in place that prevent
Get instant SAP help. Sign up for our Free Essentials Plan.
KI343
Activity type &/& does not exist for &
What causes this issue? You have not yet created activity type &V2&.How to fix this error? Enter a valid activity type.Error message extract...
KI342
Do not use cost element &1 for &2
What causes this issue? Cost element &V1& in controlling area &V3& is a cost element for internal cost allocation (with cost element ...
KI345
Processing error in CO interface: Contact SAP
What causes this issue? An internal error occurred when setting up the CO document. The SAP System searched for temporary document number &V2&...
KI346
Valuated project stock not allowed with customer stock.
What causes this issue? The entered WBS element &V1& manages a valuated project stock. At the same time, a sales order stock is managed on th...