Do you have any question about this error?
Message type: E = Error
Message class: K8 - CO Planning: Messages for Function Group KAPP
Message number: 052
Message text: No changes were carried out for the selected plan value
You want to carry out "Itemization" for key figure &V1&.
However, no plan data has been changed for this key figure. In each
plan document, the value of the values of periods &V2& - &V3& equals
zero.
The function cannot be executed.
Choose another data cell, and repeat the function if necessary.
Error message extract from SAP system. Copyright SAP SE.
K8052
- No changes were carried out for the selected plan value ?The SAP error message K8052 ("No changes were carried out for the selected plan value") typically occurs in the context of cost planning or budgeting within the SAP Controlling (CO) module. This error indicates that the system did not find any changes to apply to the selected plan value, which can happen for several reasons.
Causes:
- No Changes Made: The most straightforward reason is that the user did not make any changes to the planning data before attempting to save or execute the plan.
- Incorrect Selection: The selected planning version or period may not have any data that requires updating or may not be relevant to the changes being attempted.
- Data Locking: The planning data might be locked by another user or process, preventing any changes from being applied.
- Authorization Issues: The user may not have the necessary authorizations to make changes to the planning data.
- Technical Issues: There could be underlying technical issues, such as problems with the database or the application server.
Solutions:
- Verify Changes: Ensure that you have made the necessary changes to the planning data. Double-check the input fields and values.
- Check Selection Criteria: Review the selection criteria for the planning version and period to ensure they are correct and relevant.
- Release Locks: If data is locked, check with your system administrator or the user who has locked the data to release it.
- Review Authorizations: Ensure that you have the appropriate authorizations to make changes to the planning data. If not, contact your SAP security administrator.
- Consult Logs: Check the application logs for any additional error messages or warnings that might provide more context about the issue.
- Technical Support: If the issue persists, consider reaching out to your SAP support team or technical support for further investigation.
Related Information:
By following these steps, you should be able to identify the cause of the K8052 error and implement a solution.
Get instant SAP help. Start your 7-day free trial now.
K8051
Itemization is not possible for new plan value
What causes this issue? You want to execute the function "Line items". The data cell, however, belongs to a plan record for which no values...
K8050
No itemization is allowed for the actual key figures
What causes this issue? You want to execute the function "Line Items" for key figure &V1&. This journal entry statement is not supp...
K8053
No itemization available for prices/units.
What causes this issue? You want to execute the function "Line items" for key figure &V1& . Validation is not supported for sender ...
K8054
Initial value for sender actv. type valid only with sender cost center.
What causes this issue? You transfered the intial value in the selection criteria for the senter activity type characteristic (for example, from with...