Do you have any question about this error?
Stop googling SAP errors. Use our Free Essentials plan instead - no credit card needed. Start Now →
Message type: E = Error
Message class: K4 - Order settlement configuration tables
Message number: 030
Message text: Cost element groups overlap in sett. assgmnts &1 and &2 of structure &3
There are overlapping cost element intervals in the cost element groups
you entered as the source in settlement assignments &V1& and &V2& for
settlement structure &V3&. This means that there are cost elements that
are allocated to both settlement assignments, and the settlement to the
settlement cost element is not unique.
The problem occurred in controlling area &V4&.
When you are in the settlement structure maintenance this message is
only a warning. You can skip the message by choosing "Enter" to carry
out corrections.
When you save the settlement structure, the message appears as
information. The system always saves the settlement structure. You
should, however, correct the error as soon as possible. Otherwise
errors can occur during settlement.
Overcome the overlapping by
entering other cost element groups, or by
changing the cost element groups you have already entered.
You can display the cost element intervals for the cost element groups
you have entered by double-clicking or by choosing the display icon
next to the cost element group.
You can change the group you have entered through the menu
<ZH>Extras->Cost_element_group->Change</>. To do this, position the
cursor on the cost element group.
If you want to create a new cost element group, enter a group that has
not yet been created and choose "Enter". The system then creates the
group at your request.
You can get an overview of the settlement structure, including the cost
element groups you have used, through the menu path
<ZH>Extras->Overview_list</>
Error message extract from SAP system. Copyright SAP SE.
K4030
- Cost element groups overlap in sett. assgmnts &1 and &2 of structure &3 ?The SAP error message K4030 indicates that there is an overlap in cost element groups within settlement assignments in a specific structure. This typically occurs in the context of internal order accounting or cost center accounting when you are trying to settle costs and the system detects that the cost element groups defined for the settlement assignments conflict with each other.
Cause:
The error arises when:
- Overlapping Cost Element Groups: The cost element groups defined in the settlement assignments for the specified structures overlap. This means that the same cost elements are included in more than one group, which can lead to ambiguity in cost allocation.
- Incorrect Configuration: The configuration of cost element groups or settlement assignments may not be set up correctly, leading to overlaps.
- Multiple Assignments: There may be multiple assignments for the same cost element group in the settlement structure, causing conflicts.
Solution:
To resolve the K4030 error, you can take the following steps:
Review Cost Element Groups:
- Go to the configuration of the cost element groups involved in the settlement assignments.
- Check for any overlaps in the cost elements included in the groups.
Adjust Settlement Assignments:
- Modify the settlement assignments to ensure that each cost element group is unique and does not overlap with others.
- You may need to remove or reassign cost elements from one of the groups to eliminate the conflict.
Check Configuration:
- Ensure that the configuration for the settlement structure is correct and that there are no unintended overlaps in the definitions.
- Use transaction codes like OKO7 (for settlement structures) to review and adjust the settings.
Test Changes:
- After making adjustments, perform a test settlement to ensure that the error does not reoccur.
Consult Documentation:
- Refer to SAP documentation or help resources for detailed guidance on configuring cost element groups and settlement assignments.
Related Information:
By following these steps, you should be able to identify and resolve the cause of the K4030 error in your SAP system.
Get instant SAP help. Sign up for our Free Essentials Plan.
K4029
Select a valid variance category (->F4)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
K4028
Settlement to order items is always by cost element
What causes this issue? Settlement to order items is always by cost element, so there is no point making entries in the settlement structure.System R...
K4031
Source for assignment & not available
What causes this issue? You want to branch to the source of the settlement assignment &v1& in the display mode. However, you have not created...
K4032
Undo all selections, or use "Navigation"
What causes this issue? You have selected at least one entry and you want to branch to the "Assignments" subscreen by double-clicking or ch...