Do you have any question about this error?
Message type: E = Error
Message class: JITOUT - Messages for JIT Outbound
Message number: 809
Message text: Available quantity from stock determination is too small
Stock determination was carried out for material &v1& from summarized
JIT call &v2& item &v3&. The available quantity from stock
determination is smaller than the requested quantity. The stock
transfer of the material can therefore not be carried out in the
system.
The system carries out stock determination based on the stock
determination rule from the replenishment strategy of the control cycle
and the stock determination group from the material master.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
JITOUT809
- Available quantity from stock determination is too small ?The SAP error message JITOUT809 indicates that the available quantity from stock determination is insufficient to fulfill a Just-In-Time (JIT) delivery requirement. This error typically arises in scenarios where materials are being managed under JIT processes, and the system is unable to find enough stock to meet the demand.
Causes:
- Insufficient Stock: The most common cause is that the available stock for the material is less than the quantity required for the JIT delivery.
- Stock Determination Settings: The stock determination strategy may not be configured correctly, leading to incorrect stock availability calculations.
- Batch Management: If batch management is enabled, the specific batch may not have enough stock available.
- Reservation Issues: There may be existing reservations or allocations that are consuming the available stock.
- Lead Time Issues: The lead time for procurement may not align with the JIT delivery schedule, leading to stock shortages.
Solutions:
- Check Stock Levels: Verify the current stock levels for the material in question. Use transaction codes like MMBE to check stock availability.
- Adjust Stock Levels: If stock is insufficient, consider adjusting stock levels by:
- Creating a purchase order to procure more stock.
- Transferring stock from another location if possible.
- Review Stock Determination Configuration: Check the stock determination strategy in the configuration settings to ensure it is set up correctly. This can be done in the IMG (Implementation Guide) under:
- Logistics Execution > Shipping > Picking > Stock Determination.
- Check Reservations: Review any existing reservations or allocations that may be affecting stock availability. You can use transaction code MB22 to check and manage reservations.
- Batch Management: If batch management is in use, ensure that the batches have sufficient stock available and that the correct batch is being selected.
- Adjust Delivery Schedule: If possible, adjust the delivery schedule to allow for more time to procure the necessary stock.
Related Information:
By following these steps, you should be able to identify the root cause of the JITOUT809 error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
JITOUT808
Cancelation of goods receipt is not possible for summarized JIT call &1
What causes this issue? You want to cancel the goods receipt for the summarized JIT call &v1&. Whether the reverse posting can be carried out...
JITOUT807
Change to delivery date is valid for the entire JIT call
What causes this issue? You want to change the delivery date of a summarized JIT call that contains several items.System Response The delivery date ...
JITOUT810
Available quantity from batch determination is too small
What causes this issue? Batch determination was carried out for material &v1& from summarized JIT call &v2& item &V3&. The av...
JITOUT811
No JIT calls exist for this material document
What causes this issue? You want to reverse a material document for which no JIT calls exist. At least one of the scheduling agreements has the produ...
Click on this link to search all SAP messages.