Message type: E = Error
Message class: IW - Order Processing
Message number: 800
Message text: All capacities are available
The system has not found a capacity overload within the planning period.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
The system used the profile &V1& for the check.If you think that there must be a capacity overload, proceed as follows:
Determine whether a <DS:GLOS.basic_load>basic load</> was created.
Check that the planning period is not too great.
To do this, use the following functions:
<DS:SIMG.SIMG_CFMENUOLIAOIOI>Settings for capacity check</>
<DS:TRAN.CM99>Create capacity basic load</>
Error message extract from SAP system. Copyright SAP SE.
IW800
- All capacities are available ?The SAP error message "IW800 - All capacities are available" typically occurs in the context of capacity planning and scheduling within the SAP system, particularly in the areas of production planning (PP) or plant maintenance (PM). This message indicates that the system has determined that all available capacities (resources, such as machines or labor) are free and can be utilized for the planned operation or task.
Cause:
- Resource Availability: The error message is not necessarily an error but rather an informational message indicating that there are no capacity constraints for the operation you are trying to schedule or execute.
- Scheduling Parameters: The scheduling parameters or settings may be configured in such a way that they do not restrict the use of available capacities.
- Capacity Planning: The system has calculated that all capacities are available based on the current load and planned orders.
Solution:
- Review Scheduling: If you are expecting a capacity constraint, review the scheduling parameters and ensure that they are set correctly. Check if the operation is scheduled correctly and if the required resources are indeed available.
- Check Capacity Planning: Verify the capacity planning settings in the system. Ensure that the capacities are defined correctly in the work centers and that the load is being calculated as expected.
- Adjust Planning: If you need to restrict the use of certain capacities, consider adjusting the planning parameters or the capacity utilization settings in the work center.
- Consult Documentation: Refer to SAP documentation or help resources for more detailed information on capacity planning and scheduling.
Related Information:
IW31
(Create PM Order), IW32
(Change PM Order), or CM01
(Capacity Planning) to analyze and manage your orders and capacities.CM21
to evaluate capacity loads and see how resources are being utilized.CR01
or CR02
to ensure that they are set up correctly with the right capacities and scheduling parameters.If you continue to experience issues or if the message is causing operational problems, it may be beneficial to consult with your SAP support team or a consultant who specializes in SAP PP/PM modules.
Get instant SAP help. Start your 7-day free trial now.
IW799
********** Capacity planning messages *************
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
IW789
Structure of Goods Movements for Order Completed. Time: &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
IW801
There is a capacity overload
What causes this issue? The system has performed a capacity check. For this, it used the profile &V1&. No free capacity was determined within...
IW802
Work or duration not maintained
What causes this issue? Required information for the operation must not be entered yet.System Response A requirements allocation for operation &...