Message type: E = Error
Message class: IW - Order Processing
Message number: 008
Message text: Order with individual budget must not be assigned to WBS element
You are trying to assign the order to a WBS element, but the order
already has an individual budget.
You can not have an order with both an individual budget and an
assignment to a WBS element.
You can not assign this order to a WBS element.
Error message extract from SAP system. Copyright SAP SE.
IW008
- Order with individual budget must not be assigned to WBS element ?The SAP error message IW008 ("Order with individual budget must not be assigned to WBS element") typically occurs when there is a conflict between the budgeting settings of an order and the assignment of that order to a Work Breakdown Structure (WBS) element. Here’s a breakdown of the cause, potential solutions, and related information:
Cause:
- Budgeting Settings: The order in question is set up with an individual budget, which means it has its own budgetary constraints. However, it is being assigned to a WBS element that is also budgeted, leading to a conflict.
- Configuration Issues: The configuration settings in the system may not allow for orders with individual budgets to be linked to WBS elements that have their own budgets.
- Order Type: The type of order being used may not be compatible with WBS elements in terms of budget management.
Solutions:
Check Order Settings: Review the settings of the order to determine if it is indeed set up with an individual budget. If it is not necessary for the order to have an individual budget, consider changing the order type or settings to allow it to be assigned to the WBS element.
Change WBS Element Assignment: If the order must maintain its individual budget, consider removing the assignment of the order to the WBS element. This may involve restructuring how costs are tracked or reported.
Adjust Budgeting Configuration: If the business process allows, you may need to adjust the configuration settings in SAP to permit orders with individual budgets to be assigned to WBS elements. This may require assistance from a SAP configuration expert.
Consult Documentation: Review SAP documentation or consult with your SAP support team to understand the specific configuration settings that govern budget assignments for orders and WBS elements.
Use Alternative Order Types: If the current order type is causing the issue, consider using a different order type that does not have individual budget constraints.
Related Information:
CJ20N
(Project Builder) and KO02
(Change Order) to review and modify WBS elements and orders.Resolving the IW008 error involves understanding the relationship between orders and WBS elements in terms of budgeting. By reviewing the settings and making necessary adjustments, you can eliminate the conflict and proceed with your project management tasks in SAP. If issues persist, consulting with a SAP expert or your internal support team may be necessary.
Get instant SAP help. Sign up for our Free Essentials Plan.
IW007
Order & was already created for this notification
What causes this issue? You want to create an order for this <GL:notification>notification</>. However, order &V1& was already cr...
IW006
Plant is not a maintenance planning plant
What causes this issue? You specified a plant which is not indicated as a planning plant in your system.System Response INCLUDE 'KEINE-VERARBEI...
IW009
Changes to object class not allowed
What causes this issue? You are trying to change the object class for the <GL:maintenance_order>maintenance order</>.System Response The...
IW010
This function is only allowed for refurbishment orders; see long text
What causes this issue? Goods movements of this type can only be posted for <DS:DE.RSORD>refurbishment orders</>. For this reason, you al...
Click on this link to search all SAP messages.