How To Fix GPD2012 - &2 cannot be assigned without an exception WBS on Plant &1


GPD2012 - Overview

  • Message type: E = Error

  • Message class: GPD2 - GPD for DIMP4.71 uses message class GPD & GPD2

  • Message number: 012

  • Message text: &2 cannot be assigned without an exception WBS on Plant &1

  • Show details Hide details
  • What causes this issue?

    Exception handling in pegging refers to the way in which scrap,
    surplus, and stock difference (lost / found ) replenishments are
    handled.
    Pegging Customizing is defined to have all the exceptions pegged to
    exception WBS elements (for each pegging- relevant plant).
    Thus, these exception WBS elements must be defined for each
    pegging-relevant plant. However, such a definition, for each pegging
    relevant plant, has not been made.
    Pegging will not execute until you fix this problem.

    System Response

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    How to fix this error?

    You can take one of the following two steps to fix this problem:
    1. Go to Pegging Customizing transaction (0PEG01) and change the way
    exceptions are handled.
    2. Go to transaction PEG04 and define exception WBS elements for each
    pegging-relevant plant.

    Procedure for System Administrators


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message GPD2012 - &2 cannot be assigned without an exception WBS on Plant &1 ?
    The SAP error message GPD2012 indicates that a specific assignment cannot be made because it requires an exception Work Breakdown Structure (WBS) element in the specified plant. This error typically arises in the context of project management and controlling within SAP, particularly when dealing with project-related costs and resources.
    
    Cause: The error occurs when you attempt to assign a cost element, resource, or other project-related item to a WBS element that does not have the necessary configuration or is not set up correctly. Specifically, it indicates that the assignment cannot be processed because the WBS element is not recognized as valid for the operation you are trying to perform.
    Solution: To resolve the GPD2012 error, you can take the following steps: Check WBS Element Configuration: Ensure that the WBS element you are trying to use is correctly configured and active. You can do this by navigating to the WBS element in the Project System (PS) module

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author