Do you have any question about this error?
Message type: E = Error
Message class: GA - Allocations
Message number: 151
Message text: Plan allocation for WBS element & in version & not allowed.
WBS element &V1& is used as a sender or receiver in the plan allocation
used with version &V2&. This WBS element, however, is not a valid
sender/receiver because it is not integrated with planning.
A WBS element is plan integrated if the corresponding indicator is
activated in the WBS element's master data (current setting: "&V3&" )
and the indicator "Plan integration with Cost Center Accounting" is set
in the version (current setting "&V4&" ).
The WBS element &V1& is not a valid sender/receiver. Plan allocation
continues.
If the WBS element is to be used in plan allocation, the indicators
named above must be activated. See the current settings above to
determine which of these indicators needs to be set.
Error message extract from SAP system. Copyright SAP SE.
GA151
- Plan allocation for WBS element & in version & not allowed. ?The SAP error message GA151 indicates that there is an issue with the plan allocation for a Work Breakdown Structure (WBS) element in a specific version. This error typically arises in the context of project management and budgeting within SAP, particularly when dealing with project planning and cost allocation.
Cause of the Error:
Version Control: The error often occurs when the specified version for the WBS element is not allowed for planning or allocation. This can happen if:
- The version is not activated for planning.
- The version is set to a status that does not permit allocations.
- The WBS element is not assigned to the specified version.
WBS Element Configuration: The WBS element may not be properly configured to allow planning in the specified version.
Authorization Issues: There may be authorization restrictions preventing the user from making changes to the specified version.
Solution:
Check Version Settings:
- Go to the WBS element in question and check the version settings. Ensure that the version is activated for planning and that it allows allocations.
- You can do this by navigating to the WBS element in the Project System (PS) module and checking the version settings.
Review WBS Element Configuration:
- Ensure that the WBS element is correctly configured to allow planning in the specified version. This may involve checking the settings in the project definition and ensuring that the WBS element is assigned to the correct version.
Adjust Authorizations:
- If the issue is related to authorization, check the user roles and permissions to ensure that the user has the necessary rights to perform planning activities on the specified version.
Consult Documentation:
- Review SAP documentation or consult with your SAP support team for specific configuration settings related to versions and WBS elements.
Use Transaction Codes:
- You can use transaction codes like
CJ20N
(Project Builder) to check the WBS element and its version settings.Related Information:
By following these steps, you should be able to identify the cause of the GA151 error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
GA150
Plan allocation for order & in version & not allowed.
What causes this issue? Order &V1& is used as a sender or receiver in the plan allocation used with version &V2&. This order, however...
GA149
Cycle check with &1 completed: For details see error log
What causes this issue? During validation for the cycle definition &V1& occurred.System Response The system issues an error message and will...
GA152
Enter the cycle name and its start date.
What causes this issue? Befor you enter segments or make selections using F4 (input help), you must enter the cycle and its start date.Error message ...
GA153
No segment found.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.