How To Fix FCC1052 - Task &1 cannot start later than its sucessor &2


FCC1052 - Overview

  • Message type: E = Error

  • Message class: FCC1 - Messages in Financial Closing Cockpit

  • Message number: 052

  • Message text: Task &1 cannot start later than its sucessor &2

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message FCC1052 - Task &1 cannot start later than its sucessor &2 ?
    The SAP error message FCC1052, which states "Task &1 cannot start later than its successor &2," typically occurs in the context of project management or scheduling within SAP, particularly when dealing with network planning or project systems. This error indicates that there is a scheduling conflict between two tasks in a project or network.
    
    Cause: The error arises when: Task &1 (the predecessor) is scheduled to start after Task &2 (the successor) is supposed to start. In project management, a predecessor task must be completed before its successor can begin. If the scheduling does not respect this order, the system generates this error.
    Solution: To resolve this error, you can take the following steps: Check Task Dates: Review the start and finish dates of both tasks involved. Ensure that the predecessor task (Task &1) is scheduled to finish before the successor task (Task &2) starts. Adjust Task Scheduling: If Task &1 is incorrectly scheduled to start after Task

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.