How To Fix DPR_PROJECT063 - You cannot complete the project &1


SAP Error Message - Details

  • Message type: E = Error

  • Message class: DPR_PROJECT - Development Projects: Messages for Projects

  • Message number: 063

  • Message text: You cannot complete the project &1

  • Show details Hide details
  • What causes this issue?

    You cannot complete the project <(>&<)>V1& because the obligatory
    task &V2& has not been completed yet.

    System Response

    The system does not complete the project &V1&.

    How to fix this error?

    Complete the task &V2& or cancel the project &V1&, if required.

    Procedure for System Administrators

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message DPR_PROJECT063 - You cannot complete the project &1 ?

    The SAP error message DPR_PROJECT063, which states "You cannot complete the project &1," typically occurs in the context of project management within SAP, particularly in the Project System (PS) or Project Management (DPR) modules. This error indicates that there are certain conditions preventing the completion of the specified project.

    Causes:

    1. Incomplete Tasks or Milestones: There may be open tasks or milestones that need to be completed before the project can be finalized.
    2. Open Purchase Orders or Contracts: If there are outstanding purchase orders or contracts associated with the project, it may prevent completion.
    3. Unsettled Costs: There might be costs that have not been settled or posted against the project.
    4. Status Restrictions: The project may be in a status that does not allow for completion (e.g., "In Progress" or "On Hold").
    5. Dependencies on Other Projects: If the project is dependent on another project that is not completed, it may block the completion.
    6. Missing Documentation: Required documentation or approvals may be missing.

    Solutions:

    1. Check Project Status: Review the project status and ensure it is set to a state that allows for completion.
    2. Complete Open Tasks: Go through the project tasks and ensure all are completed or appropriately marked.
    3. Review Financial Transactions: Check for any open purchase orders, contracts, or unsettled costs that need to be addressed.
    4. Resolve Dependencies: If there are dependencies on other projects, ensure those projects are completed or resolved.
    5. Documentation and Approvals: Ensure that all necessary documentation and approvals are in place.
    6. Consult with Project Stakeholders: Engage with project stakeholders to identify any outstanding issues that may be preventing completion.

    Related Information:

    • Transaction Codes: You may use transaction codes like CJ20N (Project Builder) or CJ02 (Change Project) to review project details.
    • SAP Notes: Check SAP Notes for any known issues or patches related to this error message.
    • User Authorizations: Ensure that you have the necessary authorizations to complete the project.
    • Consult Documentation: Refer to SAP documentation or help files for more detailed guidance on project completion processes.

    If the issue persists after checking these areas, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in SAP Project Management.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant