How To Fix DPR_PROJECT004 - You cannot change the project type because the project has been released


SAP Error Message - Details

  • Message type: E = Error

  • Message class: DPR_PROJECT - Development Projects: Messages for Projects

  • Message number: 004

  • Message text: You cannot change the project type because the project has been released

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message DPR_PROJECT004 - You cannot change the project type because the project has been released ?

    The SAP error message DPR_PROJECT004 indicates that you are trying to change the project type of a project that has already been released. In SAP Project Management, once a project is released, certain attributes, including the project type, become locked to maintain the integrity of the project data and its associated processes.

    Cause:

    The primary cause of this error is that the project you are attempting to modify has been released, which means it is in a state where changes to its fundamental characteristics (like project type) are restricted. This is a safeguard to prevent inconsistencies and ensure that the project remains stable during its execution.

    Solution:

    To resolve this error, you have a few options:

    1. Unrelease the Project: If you have the necessary permissions, you can unrelease the project. This will allow you to change the project type. However, be cautious with this approach, as un-releasing a project may have implications for ongoing processes and reporting.

      • Navigate to the project in question.
      • Use the appropriate transaction code (like CJ20N for Project Builder) to access the project.
      • Look for an option to "Unrelease" the project. This may be found under the project management menu or as a button in the interface.
    2. Create a New Project: If un-releasing the project is not an option or if it is not advisable due to business processes, consider creating a new project with the desired project type. You can then transfer any relevant data or tasks from the old project to the new one.

    3. Consult with Your SAP Administrator: If you are unsure about the implications of un-releasing a project or if you do not have the necessary permissions, consult with your SAP administrator or project manager. They can provide guidance on the best course of action based on your organization's policies.

    Related Information:

    • Project Management in SAP: Understanding the project lifecycle in SAP is crucial. Projects typically go through various stages, including planning, execution, and closure. Each stage has specific rules regarding what can and cannot be changed.
    • Authorization: Ensure that you have the necessary authorizations to make changes to project settings. If you lack permissions, you will need to work with someone who has the appropriate access.
    • Documentation: Always document any changes made to project settings, especially if you unrelease a project, to maintain a clear audit trail.

    By following these steps, you should be able to address the error message and proceed with your project management tasks in SAP.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author