Do you have any question about this error?
Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 748
Message text: Order & operation &: Start date limit exceeded
Once the operation has been dispatched, the start date constraint is
violated.
Possible causes include:
The constraint date falls at a time when production is not taking place.
The capacity is already committed at the constraint date.
The operation was manually rescheduled.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Depending on the cause you can
Change the available capacity
Deallocate other operations that are committed to the capacity
Determine the time of dispatching automatically rather that manually.
Error message extract from SAP system. Copyright SAP SE.
CY748
- Order & operation &: Start date limit exceeded ?The SAP error message CY748 ("Order & operation &: Start date limit exceeded") typically occurs in the context of production planning and control, particularly when dealing with operations in a production order. This error indicates that the start date of an operation exceeds the allowed limits set in the system.
Cause:
Date Configuration: The start date of the operation is beyond the permissible limits defined in the system settings. This could be due to:
- The operation's scheduled start date being set too far in the future.
- The configuration of the planning parameters that restrict the scheduling of operations.
Capacity Constraints: If there are capacity constraints or resource availability issues, the system may not be able to schedule the operation within the defined limits.
Order Status: The status of the production order may not allow for scheduling or rescheduling of operations.
Master Data Issues: Incorrect or incomplete master data for the materials, resources, or production versions can lead to scheduling issues.
Solution:
Check Operation Dates: Review the scheduled start date of the operation in the production order. Ensure that it falls within the acceptable range defined in the system.
Adjust Planning Parameters: If necessary, adjust the planning parameters in the configuration settings to allow for a wider range of scheduling dates.
Review Capacity Planning: Check the capacity planning settings and ensure that the resources required for the operation are available during the scheduled time.
Change Order Status: If the order status is preventing scheduling, consider changing the status to allow for the necessary adjustments.
Update Master Data: Ensure that all relevant master data (materials, resources, etc.) is correctly maintained and up to date.
Consult Documentation: Refer to SAP documentation or consult with your SAP support team for specific configuration settings related to scheduling and operation limits.
Related Information:
If the issue persists after trying the above solutions, it may be beneficial to engage with your SAP support team or consult with an SAP expert for further analysis and resolution.
Get instant SAP help. Start your 7-day free trial now.
CY747
Operation & sub-operation &: Work center was changed manually
What causes this issue? The sub-operation was manually dispatched to the work center &V4& or rescheduled to it. The sub-operation was origina...
CY746
Order & operation &: Work center was changed manually
What causes this issue? The operation was manually dispatched to work center &V4& or rescheduled to it. The operation was originally to be pr...
CY749
Order & operation &: Finish date limit exceeded
What causes this issue? Once the operation has been dispatched the finish date constraint is violated. Possible causes include: The constaint date fa...
CY750
Order & operation &: Rescheduling not permitted because of status
What causes this issue? You want to reschedule an operation. A system- or user status has been set that prevents this action.System Response How to f...