Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 403
Message text: Split has not been assigned
You are trying to dispatch a split that has not been assigned.
First assign the split and then dispatch it.
Error message extract from SAP system. Copyright SAP SE.
CY403
- Split has not been assigned ?The SAP error message CY403: Split has not been assigned typically occurs in the context of the Controlling (CO) module, particularly when dealing with cost center accounting or internal orders. This error indicates that the system is unable to find a valid assignment for a split in the cost distribution process. Causes: Missing Split Assignment: The split you are trying to use has not been defined in the system. This could be due to a configuration oversight or an incomplete setup. Incorrect Configuration: The configuration settings for the split may not be properly set up in the controlling area or for the specific cost object. Data Inconsistencies: There may be inconsistencies in the master data related to cost centers, internal orders, or other relevant objects. Authorization Issues: Sometimes, the user may not have the necessary authorizations to access or modify the split assignments. Solutions: Check Split Configuration: Go to the configuration settings in SAP (Transaction code: SPRO). Navigate to
Get instant SAP help. Sign up for our Free Essentials Plan.
CY402
Operation is already dispatched
What causes this issue? You try to dispatch an operation that already has the status <ZH>dispatched</>.System Response You cannot dispat...
CY401
Capacity requirements can not be displayed
What causes this issue? You cannot display the capacity requirements for the operation since the value exceeds the length of the display field.System...
CY404
The remaining split cannot be deleted
What causes this issue? You are trying to delete the remaining split that contains the remaining requirements after an incomplete split of the capaci...
CY405
Operation was deallocated because of changes relevant to scheduling
What causes this issue? The operation was changed. The changes have effects on the operation duration and the commitment situation of the capacities....
Click on this link to search all SAP messages.