Message type: E = Error
Message class: CO - PPC order processing messages
Message number: 262
Message text: Material &: No operations exist (transaction terminated)
The combination material-plant-production version &V2& selected for the
routing does not contain any operations.
The transaction is terminated since in Customizing for the order type
you have specified that a routing MUST be used.
Create a routing or change the setting for the order type.
Error message extract from SAP system. Copyright SAP SE.
CO262
- Material &: No operations exist (transaction terminated) ?The SAP error message CO262 ("Material &: No operations exist") typically occurs in the context of production planning and control, particularly when dealing with production orders or routing. This error indicates that the system cannot find any operations associated with the specified material in the routing or production order.
Causes:
- Missing Routing: The material does not have an associated routing defined in the system.
- Incorrect Material Number: The material number entered may be incorrect or does not exist in the system.
- Inactive Routing: The routing for the material may be inactive or not valid for the specified plant.
- Missing Production Version: If the material requires a production version and it is not defined, this error can occur.
- Configuration Issues: There may be configuration issues in the production planning settings that prevent the system from finding the operations.
Solutions:
Check Routing:
- Go to transaction CA03 (Display Routing) and check if a routing exists for the material in question.
- Ensure that the routing is active and valid for the relevant plant.
Verify Material Number:
- Ensure that the material number entered is correct. You can check this in transaction MM03 (Display Material).
Check Production Version:
- If applicable, check if a production version exists for the material using transaction C223 (Maintain Production Versions).
Review Plant Settings:
- Ensure that the routing is assigned to the correct plant. You can check this in the routing details.
Check for Inactive Operations:
- If the routing exists but has inactive operations, you may need to activate them or create new operations as necessary.
Consult with Configuration Team:
- If you suspect configuration issues, consult with your SAP configuration team to ensure that the production planning settings are correctly set up.
Related Information:
Transaction Codes:
SAP Notes: Check SAP Notes for any known issues or patches related to this error message.
Documentation: Review SAP documentation on production planning and routing to understand how operations are linked to materials.
By following these steps, you should be able to identify the cause of the CO262 error and implement the appropriate solution. If the issue persists, consider reaching out to your SAP support team for further assistance.
Get instant SAP help. Start your 7-day free trial now.
CO261
Routing not released: &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CO260
Order quantity & is outside planned lot sizes & - & &
What causes this issue? The task list that exists in the order is not permitted for the desired order quantity.How to fix this error? To get a valid...
CO263
No routing selected
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CO264
Last operation is already reached
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.