Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 814
Message text: Activity & cannot have a relationship to itself
You have entered a relationship for the same activity that you have
selected for maintaining relationships.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Enter a different activity for the relationship.
Error message extract from SAP system. Copyright SAP SE.
CN814
- Activity & cannot have a relationship to itself ?The SAP error message CN814 ("Activity & cannot have a relationship to itself") typically occurs in the context of project management within SAP, particularly when dealing with network activities in Project System (PS) or when managing work breakdown structures (WBS). This error indicates that there is an attempt to create a relationship (dependency) between an activity and itself, which is not allowed.
Cause:
- Self-Referencing Relationship: The most common cause of this error is that a user is trying to establish a predecessor or successor relationship where the same activity is being referenced. For example, if Activity A is set to start after Activity A, it creates a circular reference that is logically incorrect.
Solution:
Check Relationships: Review the relationships defined for the activity in question. Ensure that you are not trying to link the activity to itself.
- Go to the network or activity details and check the "Relationships" tab.
- Remove any self-referencing relationships.
Correct Activity Links: If you need to establish a dependency, ensure that you are linking to a different activity.
- Identify the correct predecessor or successor activities and set the relationships accordingly.
Review Activity Configuration: If the error persists, check the configuration of the activity itself. Ensure that all settings are correct and that there are no other underlying issues.
Consult Documentation: If you are unsure about how to set up relationships correctly, refer to SAP documentation or user manuals related to Project System and activity management.
Related Information:
CN21
(Create Network), CN22
(Change Network), or CJ20N
(Project Builder) to manage activities and their relationships.By following these steps, you should be able to resolve the CN814 error and correctly manage your project activities in SAP.
Get instant SAP help. Start your 7-day free trial now.
CN813
Enter activity number
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN812
Activity & does not exist in network &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN815
Standard network has several alternatives. Choose one
What causes this issue? You must maintain an alternative in order to maintain a relationship to another standard network.System Response INCLUDE NA_...
CN816
Standard network & & being processed. Rel. cannot be maintained
What causes this issue? The external standard network you have entered is currently being used by another user and is locked. You cannot maintain the...
Click on this link to search all SAP messages.